Ground zero building struggles to find tenants

 

 NEW YORK — An 80-story skyscraper under construction at ground zero will have to stop at seven stories unless the developer can line up more tenants, planners said Monday, adding to problems that have plagued the $11.7 billion World Trade Center project.

Silverstein Properties Inc. said it is still looking for tenants to fill the first 10 floors of Three World Trade Center, the third-highest building in the planned office complex. Without those leases, the Port Authority of New York and New Jersey will not guarantee the financing that Silverstein needs to finish the building.

Construction would end at the “podium” level on the seventh floor, with the option of building up later on, and the floors below would be filled mainly with retail stores.

Many companies in New York are reluctant to invest in new offices because of the poor economy, and dozens are negotiating lower rents as five-year leases signed before the housing crash begin to expire. But both Silverstein and the Port Authority said they are confident the developer can get enough tenants lined up.

“We are currently speaking with a number of potential tenants and remain fully optimistic that we will sign a lease in time to complete the tower as scheduled in 2015,” Larry Silverstein, the company’s chief executive, said in a written statement.

Mayor Michael Bloomberg said that he would be disappointed if Three World Trade did not go higher, but that the city would not extend any aid to keep it going. The most important part of the project, he said, is laying the infrastructure for future construction.

“If you did that and you couldn’t keep building up, I think that’s a shame,” Bloomberg told reporters. “But there are things that should depend on the marketplace and investors. That should be up to them.”

The 10-story “pre-lease” requirement is included in a 2010 agreement between Silverstein and the Port Authority.

The second-highest building planned for the complex, the 88-story Two World Trade Center, is also on hold because of a lack of tenants. Workers are finishing the underground parts of that building but will cap it at ground level.

The difficulty in finding tenants comes amid other problems that have dogged the World Trade Center project.

Work on a museum at ground zero has stopped because of a dispute between the Port Authority and the National September 11 Memorial & Museum over who should pay for infrastructure costs. The Port Authority says the foundation owes it $300 million, while the foundation says the bill should be closer to $140 million.

Planners had hoped to open the museum on the 11th anniversary of the 2001 terrorist attacks, but Bloomberg has said that’s no longer possible.

Work has also slowed on One World Trade Center, the spire formerly known as the Freedom Tower. Workers had been averaging a floor a week in mid-2011, but photographs have shown little growth in recent months.